A view of the Karnes Natural Gas Compressor Station.

Karnes Natural Gas Compressor Station

Sargent & Lundy provided mechanical construction and functional testing for full operation readiness of natural gas compressor station.

Client

BPX Energy

Location

Karnes, Texas

Milestones

  • Mechanical completion: February 2021
  • Introduction of nitrogen and facility leak check: February 2021
  • Introduction of hydrocarbons: April 2021
  • Plant startup and turnover: May 2021

Jack Kuskie

Director of Business Development

312-269-6901

Email

Natural Gas Compressor Central Distribution Facility

Project Details

Client

BPX Energy

Location

Karnes, Texas

Milestones

  • Mechanical completion: February 2021
  • Introduction of nitrogen and facility leak check: February 2021
  • Introduction of hydrocarbons: April 2021
  • Plant startup and turnover: May 2021

Jack Kuskie

Director of Business Development

312-269-6901

Email


Project Highlights

  • Major mechanical construction completion achieved.
  • Safe introduction of all hydrocarbons, fluids, and gases into the facility.
  • Successful plant startup, turnover, and readiness for services.
  • Project completed with no injuries or accidents.

Project Description:

The Karnes natural gas compressor central distribution facility is owned by BPX and was designed for a capacity of 84 million standard cubic feet per day (MMSCFD). The facility includes dehydration capability.

Sargent & Lundy BPX Energy Karnes 3

The commissioning work involved multiple steps to ensure complete and successful construction for safe facility startup and operation. These steps included:

  • Verify and manage mechanical completion.
  • Implement and verify piping and equipment cleanout.
  • Manage the introduction of inert gases and fluids into the facility for initial functional testing.
  • Manage the introduction of process fluids and hydrocarbons into the facility for final functional testing of equipment.
  • Provide oversight and assist vendors and contractors as equipment is brought online.
  • Facilitate the plant startup and final turnover to BPX.

Project Scope:

The BPX Infrastructure team engaged Sargent & Lundy to manage the planning, scheduling, documentation, verification, and functional testing of the 84-MMSCFD-capacity natural gas compressor station, which includes dehydration capability. Sargent & Lundy was involved through the final construction phase and turned the fully operational facility over to BPX operations.

The scope encompassed the following primary tasks:

  • Set up the pre-startup safety review (PSSR) process and delegate responsibilities to personnel.
  • Conduct oversight of mechanical completion in conjunction with the construction manager with primary focus on confirming the facility is constructed per design and verifying the facility will operate as designed.
  • Ensure equipment and piping are cleared of debris and a plantwide leak check is performed using compressed air. Repair any identified leaks prior to proceeding with further commissioning activities.
  • Purge all equipment and piping of air using nitrogen to achieve an oxygen-free environment within the equipment and piping.
  • Add water to all liquid-service equipment so testing can begin. Function-test devices and equipment with liquid in the vessels and tanks, and pressure from nitrogen in all other equipment and piping.
  • Introduce hydrocarbons into the facility and perform final functional testing and commissioning of the remaining equipment.
  • Hand over the plant to BPX once all equipment is online and fully operational.

The project deliverables included:

  • Development of a commissioning schedule.
  • Development and implementation of blowout plans, nitrogen purge plans, liquids introduction plans, and fuel gas introduction plans including the review of procedures and piping and instrumentation diagrams (P&ID) and conducting risk assessment and what-if analyses.
  • Development and management of punch list of action items needed to drive project to completion.
  • As-built P&ID redlines.
  • Primary source verification (PSV) and management.
  • Equipment verification and management.
  • Pre-startup safety review turnover books.

Read more about our oil & gas services.