Key Crossing Reliability Initiative

BGE Key Crossing 230-kV Transmission Reliability Project Baltimore, Maryland Client: Baltimore Gas and Electric Company Project Highlights: 2.25 miles of new ACCR transmission conductor. Eight new transmission poles: five poles erected in the Patapsco River and equipped with vessel collision … Continue reading

Posted in Electric Grid Infrastructure, Projects | Comments Off on Key Crossing Reliability Initiative

Ten West Link Transmission Line

Ten West Link Transmission Line Tonopah, Arizona, to Blythe, California Client: Lotus Infrastructure Partners Project Highlights: The 500-kilovolt transmission line is recognized by the Department of Energy and Biden-Harris administration as a critical infrastructure project for the Desert Southwest region. … Continue reading

Posted in Electric Grid Infrastructure, Projects | Comments Off on Ten West Link Transmission Line

69 kV & 138 kV Infrastructure Improvement Projects for AEP

Print This Page 69kV & 138kV Infrastructure Program Client: American Electric Power (AEP) Sargent & Lundy EPC joint venture with EC Source Services: Right-of-way acquisition/public outreach Engineering and design/procurement Construction, testing, commissioning Project Description: American Electric Power is executing Infrastructure … Continue reading

Posted in Electric Grid Infrastructure, Projects | Comments Off on 69 kV & 138 kV Infrastructure Improvement Projects for AEP

New and Modified Substations for 138 kV & 69 kV Improvements Project near Alexandria, Indiana

Print This Page Alexandria Area Improvements near Muncie, Indiana Client: American Electric Power Sargent & Lundy EPC Joint Venture with EC Source Services Engineering and Design /Procurement Construction, Testing, and Commissioning Project Description: The Alexandria Area Improvements Project near Muncie, … Continue reading

Posted in Electric Grid Infrastructure, Projects | Comments Off on New and Modified Substations for 138 kV & 69 kV Improvements Project near Alexandria, Indiana

Sister Lakes Upgrades Project for 69 kV Infrastructure Improvement

Sister Lakes Upgrades Project near Hartford, Michigan Client: American Electric Power Project Description: Sargent & Lundy EPC Joint Venture with EC Source Services Right-of-way acquisition/public outreach Engineering and design/procurement Construction, testing, and commissioning The Sister Lakes Upgrades Project near Hartford, … Continue reading

Posted in Electric Grid Infrastructure, Projects | Comments Off on Sister Lakes Upgrades Project for 69 kV Infrastructure Improvement

Maine Power Substation Additions

Maine Power Substation Additions Augusta, Maine Client: Central Maine Power Print This Page Project Highlights: Transmission line engineering and design Technical specifications for material and equipment Testing and commissioning Project Description: Sargent & Lundy is teaming with Cianbro Corp. (Pittsfield, ME) … Continue reading

Posted in Electric Grid Infrastructure, Projects | Comments Off on Maine Power Substation Additions

Top Crop Wind Farm Project

Top Crop Wind Farm Pontiac, Illinois Client: Horizon Wind Energy, LLC Print This Page Project Highlights: Transmission line engineering and design Substation engineering and design Collection system engineering and design Material and equipment procurement support Construction field services Project Description: Sargent … Continue reading

Posted in Electric Grid Infrastructure, Projects, Renewable Energy | Comments Off on Top Crop Wind Farm Project

Rebuilding Project for 138 kV Infrastructure Improvements – Longview Heights to Marshall Project

Print This Page Longview Heights to Marshall Project near Longview Texas Client: American Electric Power Project Description: Sargent & Lundy EPC Joint Venture with EC Source Services Public outreach Engineering and design /procurement Construction, testing, and commissioning The Longview Heights … Continue reading